Buckley SFB MEB Timeline MH

Wow, We basically started our package and the time line matches so well. Your dates are just one day after and one day before! I hope tomorrow will be the day I sign !
That is good to hear, hopefully everything goes in your favor. I honestly put off on signing it from last week, because I wanted to consult with someone from ODC first to express my concerns and weigh out my options without pushing the timeline back drastically for it to not rule in my favor.
 
IRILO Stage
December 16, 2025- NARSUM was made and submitted by the MH provider
January 12, 2026- Profile was put into code 37 & PEBLO reached out
January 15-19, 2026- Was admitted and released from the inpatient program for an attempt
January 22, 2026- MEB interview sheet submitted to PEBLO
February 7, 2026- CIS was signed and submitted to PEBLO (Do Not Retain)
February 11, 2026- PEBLO sent package to AFPC for review
February- March 2026- Reaching out to PEBLO for updates (Was told they are backed up and there will be delays: 30–45-day delay)
March 31, 2026- FL4 assigned/ Directed to complete Full MEB

MEB/ IDES Stage
March 31, 2026- Met up with PEBLO for briefing, selected IDES, signed and submitted required documents
April 2, 2026- PEBLO submitted case to VA (Now waiting for contact from MSC)
April 4, 2026- VA MSC reached out to schedule a phone interview
April 6, 2026- Phone interview with MSC (7-10 days for contractor to make contact for C&P Exams)
April 7, 2026- VA contractor reached out to schedule C&P Exams
April 9, 2026- Mental Health C&P Exam
April 14, 2026- Audio, General, Lab C&P Exams
April 20, 2026- Follow-up C&P Exam p.1
April 21, 2026- Follow-up C&P Exam p.2
May 5, 2026- Package referred to IPEB (PEBLO did in-brief; provider needs to revise NARSUM due to incorrect format before it is sent to PEB)
May 12, 2026- Signed Form 618, selected election on IMR, and submitted package with LOE to PEBLO

IPEB/ IDES Stage
May 12, 2026- Received 1st FSS email (AFPC reviews package before IPEB makes determination)
 
Wow, that seems fast. From last C&P to MEB decision was only 2 weeks? Apr 21 - May 5th? My last C&P exam is tomorrow.
 
IRILO Stage
December 16, 2025- NARSUM was made and submitted by the MH provider
January 12, 2026- Profile was put into code 37 & PEBLO reached out
January 15-19, 2026- Was admitted and released from the inpatient program for an attempt
January 22, 2026- MEB interview sheet submitted to PEBLO
February 7, 2026- CIS was signed and submitted to PEBLO (Do Not Retain)
February 11, 2026- PEBLO sent package to AFPC for review
February- March 2026- Reaching out to PEBLO for updates (Was told they are backed up and there will be delays: 30–45-day delay)
March 31, 2026- FL4 assigned/ Directed to complete Full MEB

MEB/ IDES Stage
March 31, 2026- Met up with PEBLO for briefing, selected IDES, signed and submitted required documents
April 2, 2026- PEBLO submitted case to VA (Now waiting for contact from MSC)
April 4, 2026- VA MSC reached out to schedule a phone interview
April 6, 2026- Phone interview with MSC (7-10 days for contractor to make contact for C&P Exams)
April 7, 2026- VA contractor reached out to schedule C&P Exams
April 9, 2026- Mental Health C&P Exam
April 14, 2026- Audio, General, Lab C&P Exams
April 20, 2026- Follow-up C&P Exam p.1
April 21, 2026- Follow-up C&P Exam p.2
May 5, 2026- Package referred to IPEB (PEBLO did in-brief; provider needs to revise NARSUM due to incorrect format before it is sent to PEB)
May 12, 2026- Signed Form 618, selected election on IMR, and submitted package with LOE to PEBLO

IPEB/ IDES Stage

May 12, 2026- Received 1st FSS email (AFPC reviews package before IPEB makes determination)
May 14, 2026- Received 2nd FSS email (PEBLO will discuss PEB findings/ percentage: AF Form 356 & 1180)
 
That is good to hear, hopefully everything goes in your favor. I honestly put off on signing it from last week, because I wanted to consult with someone from ODC first to express my concerns and weigh out my options without pushing the timeline back drastically for it to not rule in my favor.
Just got the email stating peb findings with peblo officer lol so yes our timeline
IRILO Stage
December 16, 2025- NARSUM was made and submitted by the MH provider
January 12, 2026- Profile was put into code 37 & PEBLO reached out
January 15-19, 2026- Was admitted and released from the inpatient program for an attempt
January 22, 2026- MEB interview sheet submitted to PEBLO
February 7, 2026- CIS was signed and submitted to PEBLO (Do Not Retain)
February 11, 2026- PEBLO sent package to AFPC for review
February- March 2026- Reaching out to PEBLO for updates (Was told they are backed up and there will be delays: 30–45-day delay)
March 31, 2026- FL4 assigned/ Directed to complete Full MEB

MEB/ IDES Stage
March 31, 2026- Met up with PEBLO for briefing, selected IDES, signed and submitted required documents
April 2, 2026- PEBLO submitted case to VA (Now waiting for contact from MSC)
April 4, 2026- VA MSC reached out to schedule a phone interview
April 6, 2026- Phone interview with MSC (7-10 days for contractor to make contact for C&P Exams)
April 7, 2026- VA contractor reached out to schedule C&P Exams
April 9, 2026- Mental Health C&P Exam
April 14, 2026- Audio, General, Lab C&P Exams
April 20, 2026- Follow-up C&P Exam p.1
April 21, 2026- Follow-up C&P Exam p.2
May 5, 2026- Package referred to IPEB (PEBLO did in-brief; provider needs to revise NARSUM due to incorrect format before it is sent to PEB)
May 12, 2026- Signed Form 618, selected election on IMR, and submitted package with LOE to PEBLO

IPEB/ IDES Stage
May 12, 2026- Received 1st FSS email (AFPC reviews package before IPEB makes determination)
May 14, 2026- Received 2nd FSS email (PEBLO will discuss PEB findings/ percentage: AF Form 356 & 1180)
same! Now waiting for legal and then to move on to getting my orders!
 
IRILO Stage
December 16, 2025- NARSUM was made and submitted by the MH provider
January 12, 2026- Profile was put into code 37 & PEBLO reached out
January 15-19, 2026- Was admitted and released from the inpatient program for an attempt
January 22, 2026- MEB interview sheet submitted to PEBLO
February 7, 2026- CIS was signed and submitted to PEBLO (Do Not Retain)
February 11, 2026- PEBLO sent package to AFPC for review
February- March 2026- Reaching out to PEBLO for updates (Was told they are backed up and there will be delays: 30–45-day delay)
March 31, 2026- FL4 assigned/ Directed to complete Full MEB

MEB/ IDES Stage
March 31, 2026- Met up with PEBLO for briefing, selected IDES, signed and submitted required documents
April 2, 2026- PEBLO submitted case to VA (Now waiting for contact from MSC)
April 4, 2026- VA MSC reached out to schedule a phone interview
April 6, 2026- Phone interview with MSC (7-10 days for contractor to make contact for C&P Exams)
April 7, 2026- VA contractor reached out to schedule C&P Exams
April 9, 2026- Mental Health C&P Exam
April 14, 2026- Audio, General, Lab C&P Exams
April 20, 2026- Follow-up C&P Exam p.1
April 21, 2026- Follow-up C&P Exam p.2
May 5, 2026- Package referred to IPEB (PEBLO did in-brief; provider needs to revise NARSUM due to incorrect format before it is sent to PEB)
May 12, 2026- Signed Form 618, selected election on IMR, and submitted package with LOE to PEBLO

IPEB/ IDES Stage

May 12, 2026- Received 1st FSS email (AFPC reviews package before IPEB makes determination)
May 14, 2026- Received 2nd FSS email (PEBLO will discuss PEB findings/ percentage: AF Form 356 & 1180)
May 15, 2026- Receiving briefing from leadership of PEB results as well as PEBLO briefing in detail (document review, ratings, and compensation)
 
Top